Repairs to Interior/Exterior, Readiness Center Building Clinton Readiness Center Clinton, Missouri
AI helper
The bidder agrees to complete the work within 150 working days from the date the notice of intent to award is issued as modified by additional days added by the owners acceptance of alternates, if applicable. the bidder agrees to complete the work within 150 working days from the date the notice of intent to award is issued
Bidders must complete the MBE/WBE/SDV compliance form and adhere to prevailing wage laws. a condition for remaining in competition for award is the satisfactory completion of this form for each minority womanservice disabledveteranowned firm
The bidder agrees to pay to, or allow the state as liquidated damages the sum of 1,000 for each working day thereafter that the entire work is not substantially complete. the bidder further agrees to pay to, or allow the state as liquidated damages the sum of 1,000 for each working day thereafter that the entire work is not substantially complete.
Failure to comply with federal work authorization or knowingly employing unauthorized aliens can lead to contract cancellation and debarment. if found to be in violation of this requirement or any applicable laws, and if the state of missouri has reasonable cause to believe that the contractor has knowingly employed individuals who are not eligible to work in the united states, the state shall have the right to cancel the contract immediately without penalty or recourse and suspend or debar the contractor from doing business with the state.