Sources sought for maintenance dredging of Texas City Ship Channel main channel and turning basin. Work includes pipeline or hopper dredging, completion in 240 calendar days. Estimated construction price range between $10M and $25M. Performance and payment bonds required within 5 days after award; work begins within 10 days of notice to proceed. Liquidated damages $4,328 per day of delay. Responses due November 7, 2026. Interested firms must register in SAM. gov. NAICS ****, PSC Z1KB.
The completion time of the work is 240 calendar days. The completion time of the work is 240 calendar days.
Responses shall indicate specialized experience in dredging deep draft navigation channels. demonstrate experience in completing work outlined under the paragraph above for project information
Liquidated damages of $4,328 per calendar day of delay. the contractor shall pay liquidated damages to the government in the estimated amount of 4,**** for each calendar day of delay
Firms failing to provide all required information may be excluded. firms responding to this announcement, who fail to provide all required information requested and outlined above, may be excluded from further consideration
The estimated construction price range is between $10,000,000 and $25,000,000. the estimated construction price range for this project is: between 10,000,000 and 25,000,000