This ITB is for the construction of boating access at Coyote Creek in the Fern Ridge Wildlife Area for the Oregon Department of Fish and Wildlife. Bids must be submitted through the OregonBuys system by September 3, 2026, at 3:00 pm PST. A mandatory prebid conference is scheduled for August 19, 2026, at 11:00 am PST in Eugene, OR. The project is subject to Build America, Buy America Act requirements. Liquidated damages of **** per calendar day apply for late completion.
Award will be made to the responsible bidder submitting the lowest responsive bid. award will be made to the responsible bidder submitting the lowest responsive bid
Bidders must be licensed with the state of Oregon construction contractors board CCB prior to bidding on public improvement contracts. bidder must be licensed with the state of oregon construction contractors board ccb prior to bidding onpublic improvement contracts oar ****.
Liquidated damages of **** per calendar day will apply for failure to complete the project by the substantial completion date. liquidated damages of **** per calendar day will apply to the contract resulting from this itb for failure tocomplete the project by the substantial completion date
A mandatory prebid conference will be held on August 19, 2026, at 11:00 am PST. a mandatory prebid conference will be held on august 19, 2026 at 11: 00 am pst, located at **** cantrellroad, eugene, or ****.
Deadline for solicitation protests, requests for change, requests for clarification, and questions is August 26, 2026, at 3:00 pm. deadline for solicitation protests, requests for change, requests for august 26, 2026 at 3: 00 pm clarification, requests for approval of equivalents, and questions
Bids may be considered nonresponsive and rejected if the bid includes nonapproved equivalents where approval is required. bids may be considered nonresponsive and rejected if the bid: includes nonapproved equivalents where approval is required
****