The project involves creating 18 temporary beach berms using existing sand at Hampton Beach State Park. Work must commence no earlier than October 2, 2026, and be completed by 2:00 PM on October 15, 2026. Bids are accepted on official forms. The successful bidder must have experience in site work and excavation for a minimum of five years. Performance and payment bonds are required for bids of $75,000 or more. The award is generally based on the lowest base bid price.
The work shall commence no earlier than October 2, 2026 and be completed no later than 2:00 pm on October 15, 2026.
Warranties required by the contract documents shall commence on the date of substantial completion unless otherwise provided in the certificate of substantial completion.
In most cases the proposal submitted by the qualified bidder with the lowest base bid price shall be selected.
The successful bidder shall provide evidence upon request that they have been in the site work and excavation business successfully performing this type, scale, and quality of work for a minimum of five years.
If the contractor fails to complete all of the work or sections of the project, within the time specified in the contract, the sum given in the schedule that follows will be deducted from any money due the contractor.
Bidders shall visit the site and be responsible for having ascertained pertinent local conditions such as: location, accessibility, general character of the site or building, the character and extent of existing work within or adjacent to the site, and any other work being performed thereon at the time of the submission of this bid.
Failure to execute the contract within 15 days after the contract has been mailed or otherwise delivered to the successful bidder shall be just cause for the cancellation of the award and the forfeiture of the proposal guaranty.