Sealed bids due December 1, 2026, 10:30 AM. Work includes removal of existing synthetic turf, base preparation, installation of new turf with shock pad, markings, goal footings, Gmax testing, and 8-year warranty. Non-mandatory prebid conference on November 18, 2026. Bid security 10% of total bid. Performance and payment bonds 100% each. Prevailing wages apply. Completion in 30 working days. Liquidated damages $1,500/day. Award to lowest responsive, responsible bidder.
Work shall be completed by contractor in 30 working days as specified in the contract documents. work shall be commenced within ten (10) working days of the date stated in the districts notice to proceed and shall be completed by contractor in 30 working days
The contract calls for monthly progress payments based upon the percentage of the work completed. the contract call for monthly progress payments based upon the percentage of the work completed
An eight-year turf warranty is included. installation of new synthetic turf with shock pad, soccer and flag football markings, soccer goal footings and anchors, gmax testing, and an eightyear turf warranty
The contract is awarded to the lowest responsive, responsible bidder based on total base bid alone. district shall award the contract for the project to the lowest responsive, responsible bidder as determined by the district from the total base bid alone
Bidders must be licensed contractors in classifications General A or B, C27, or **** and registered with the Department of Industrial Relations. each bidder shall be a licensed contractor pursuant to sections **** et seq. of the business and professions code in the following classifications. . . general a or general b, c27, or ****
Liquidated damages of $1,500 per working day for delay. contractor shall pay to the district 1, 500/day as fixed and liquidated damages. . . for each working day of delay until the work is fully completed
A nonmandatory prebid conference is scheduled for November 18, 2026, at 10:30 AM. a nonmandatory prebid conference is scheduled for november 18, 2026, at 10: 30 a. m. to review the projects existing conditions at **** franklin high rd
Bid protests must be filed in writing within 5 calendar days after the bid opening date. the protest must: be filed in writing within five (5) calendar days after the bid opening date