Turnkey renovation of Thomas Auditorium at Blue Ridge Community College. Work includes replacing theater seating, flooring, stage curtains, stage lighting, AV system upgrades, and painting. NC licensed general contractor required. Proposals due December 9, 2026 at 2:00 PM. Non-mandatory meeting November 25, 2026. Work must be completed by May 31, 2027. Liquidated damages of $500 per day. 1-year workmanship warranty required. Payment and performance bonds required for proposals over $300,000. Bid bond required for proposals over $500,000. Physical samples required for fabrics. Contractor responsible for all permits, disposal, and temporary utilities.
Work must be completed by May 31st, 2027. The notice states: work must be completed by may 31st, 2027.
No deposit will be paid. A payment request for stored materials may be requested for delivered materials verified and stored in a bonded warehouse. The document states: neither henderson county nor blue ridge community college will pay any deposit.
A 1-year written workmanship warranty is required. The document states: the contractor is required to provide a 1 year written workmanship warranty.
The project will be awarded based on the base bid. The document states: project will be awarded based on base bid.
Must be a NC licensed general contractor. The document states: you must be a nc licensed general contractor to bid this job and you must include a copy of your licensure in your bid package.
Liquidated damages of $500 per day will be applied past the date of substantial completion. The document states: liquidated damages of 500 per day will be applied, per day past the date of substantial completion.
Physical samples are required for fabrics and acoustic panel reupholstery. The document states: all fabrics require a physical sample to be submitted to brcc for approval before ordering.
Last day for questions is November 30th, 2026 at 4:00 PM. The document states: last day for questions: november 30th, 2026 at 4: 00pm.