Bids for the construction of AG Sports Complex Pickleball Lights (Phase 2 lighting improvements) are due by 2:00 p. m. on October 8, 2026. A mandatory prebid meeting is scheduled for September 24, 2026, at 10 a. m. at 700 Mercey Springs Rd, Los Banos, CA 93635. The time for completion is 90 working days. Bidders must have a current and active California state contractor license (Class A General Engineering or Class C10 Electrical). The project is subject to prevailing wage requirements.
One year warranty period is specified in the contract documents. 42 one 1 year warranty period
The successful bidder must have a current and active California state contractors license: class a information for bidders 410 general engineering contractor or, class c10 electrical contractor
Contractor shall pay owner eight hundred dollars **** for each day that passes after the time specified in paragraph 2 herein. contractor shall pay owner eight hundred dollars **** for each day that passes after the time specified in paragraph 2 herein.
A mandatory prebid meeting and project site tour will be held on September 24, 2026. a mandatory prebid meeting and project site tour will be held on september 24, 2026 at the ag sportscomplex.
The contractor shall review, approve and submit to the engineer all shop drawings, production data and samples as may be necessary for prosecution of the work. the contractor shall review, approve and submit to the engineer all shop drawings, production data and samples as may be necessary for prosecution of the work
Bid protests must be submitted in writing to the owner before 5:00 p. m. on the fifth business day following the issuance of the notice of intent to award. any bid protest must be submitted in writing to the owner before 5: 00 p. m. on the fifth 5 th business dayfollowing the issuance of the notice of intent to award.
If the owner determines that a protest is frivolous, the protesting bidder may be determined to be nonresponsive and/or nonresponsible and that bidder may be determined to be ineligible for future contract awards. if the owner determines that a protest is frivolous, the protesting bidder may be determined to be nonresponsive and/or nonresponsible and that bidder may be determined to be ineligible for future contract awards.