Mandatory prebid meeting on November 3, 2026 at 9:00 AM CT at Marrs Middle School. Bids due December 1, 2026 at 2:00 PM CT. Bid security of 5% required. Substantial completion by July 15, 2027. Liquidated damages $500 per day. One-year warranty required. Questions due November 12, 2026 via email.
Substantial completion must be achieved by July 15, 2027. Substantial completion of the work shall be achieved not later than july 15, 2027.
Applications for payment may be submitted up to twice monthly, with retainage of 10% reduced to 5% after 50% completion. Retainage in the amount of 10 of the amount of each application for payment shall be retained from each payment until the work is 50 completed.
Contractor provides a one-year warranty from substantial completion. Contractors one 1 year warranty set forth in the general terms and conditions. . . shall both run for a period of one 1 year from the date of substantial completion.
Contractor must have valid licenses and use qualified workers. All work must be done in accordance with best trade practices using qualified workers. Qualified workers shall mean at least one 1 experienced journeyman for every two 2 workers on the jobsite.
Liquidated damages of $500 per day for late substantial completion. Contractor shall pay to district as liquidated damages the sum of **** per day for each calendar day after the day set for substantial completion.
Mandatory prebid meeting at Marrs Middle School. Ops will conduct a mandatory prebid meeting for interested bidders at marrs middle school. . . on november 3, 2026, at 9: 00 am central time.
Questions must be submitted by November 12, 2026. Deadline for submission of questions november 12, 2026
Bids not attending mandatory prebid meeting will be returned unopened. Proposals received from bidders not attending the prebid meeting will be returned unopened.