USA | MO | COLE COUNTY | JEFFERSON CITY Small City
Office Of Administration - MO
Replace HVAC System Troop G Headquarters and Crime Lab Willow Springs
AI helper
The bidder agrees to complete the work within 120 working days from the date the notice of intent to award is issued as modified by additional days added by the owners acceptance of alternates, if applicable. the bidder agrees to complete the work within 120 working days from the date the notice of intent to award is issued
The bidder further agrees to pay to, or allow the state as liquidated damages the sum of 500 for each working day thereafter that the entire work is not substantially complete. the bidder further agrees to pay to, or allow the state as liquidated damages the sum of 500 for each working day thereafter that the entire work is not substantially complete.
If found to be in violation of this requirement or any applicable laws, and if the state of missouri has reasonable cause to believe that the contractor has knowingly employed individuals who are not eligible to work in the united states, the state shall have the right to cancel the contract immediately without penalty or recourse and suspend or debar the contractor from doing business with the state. if found to be in violation of this requirement or any applicable laws, and if the state of missouri has reasonable cause to believe that the contractor has knowingly employed individuals who are not eligible to work in the united states, the state shall have the right to cancel the contract immediately without penalty or recourse and suspend or debar the contractor from doing business with the state.
Bid Close Date: