Commbuys - Department Of Transportation - MA
Culvert Replacement
MassDOT Berkshire Line Track Improvements Phase V: Lee, lenoxand Pittsfield
MassDOT Berkshire Line Track Improvements Phase V: Lee, Lenox and Pittsfield Install approximately 10. 7 track miles of 136RE continuous welded rail ( CWR) from approximately MP 72 to MP 86; installation of three new turnouts; replacement of five private farm crossings; surfacing and aligning of approximately 11. 7 miles of track; replacement of up to 1, 700 timber crossties; approximately 1. 5 miles of full- depth track construction; installation of new bridge timbers on bridges ****, ****, ****, ****, **** and ****; cleaning and application of corrosion protection on top flanges of steel members; anchorage repairs at bridges ****, ****, and ****; installation of new walkway on bridges ****, ****, **** and ****
Bid Close Date: