USA | NH | MERRIMACK COUNTY | CONCORD Small City
City Of Concord-NH
B14- 27 Pump Station No. 4 Demolition
Pump Station No. 4 demolition project Demolition of pump station no. 4, including all materials, supplies, tools, equipment, labor and other services necessary for construction and completion
AI helper
Work must be substantially complete within 90 calendar days and finally complete within 120 calendar days from commencement. 90 calendar days from commencement of work for substantial completion. 120 calendar days from commencement of work for final completion.
Progress payments are made within 30 days after receipt of invoice. Retainage is 10% until work is 50% complete, then reduced to 5%, and 2% held during warranty period. the city shall pay the service provider within thirty 30 days after receipt of the service providers invoice.
All parts and labor related to construction contracts must be guaranteed and include a warranty. All parts and labor related to construction contracts must be guaranteed and include a warranty.
Contractors must have adequate financial resources, necessary experience, organization, technical and professional qualifications, skills and facilities, and be able to comply with completion schedule. have adequate financial resources for performance or have the ability to obtain such resources as required during performance
Liquidated damages of $1,000 per calendar day for delays in substantial or final completion. liquidated damages will be in the amount of 1, 000 for each calendar day of delay from the date established for substantial completion
Protests regarding the request for proposals must be filed no later than 15 calendar days before the proposal due date. protests regarding the request for proposals shall be filed as soon as the basis for protest is known to the service provider, but in no event later than fifteen 15 calendar days before the proposal due date
Failure to submit all required documents, quote all items, or comply with submission requirements may disqualify the proposal. failure to quote on all items may disqualify the proposal.