Fayette County is soliciting bids for the replacement of a double 36-inch diameter corrugated metal pipe CMP system with a 7ft x 6ft concrete box culvert near 250 Greenfield Circle. The project includes utility coordination, grading, and asphalt paving. Bids must be submitted in a sealed opaque envelope. The award will be made to the lowest responsive, responsible bidder. The contractor must be GDOT prequalified in work class 500 or 513 and guarantee work for 12 months from substantial completion. A $30,**** allowance is included for extra work.
The county's standard payment terms are net 30. the countys standard payment terms are net 30.
The contractor shall warranty and guarantee all materials supplied, equipment furnished, and work performed to be free from defects resulting from faulty materials supplied or workmanship for a period of twelve 12 months from the date of substantial completion. the contractor shall warranty and guarantee all materials supplied, equipment furnished, and work performed to be free from defects resulting from faulty materials supplied or workmanship for a period of twelve 12 months from the date of substantial completion.
Award will be made to the lowest responsive, responsible bidder, taking into consideration payment terms, vendor qualifications and experience, quality, references, any exceptions listed, and/or other factors deemed relevant in making the award. award will be made to the lowest responsive, responsible bidder, taking into consideration payment terms, vendor qualifications and experience, quality, references, any exceptions listed, and/or other factors deemed relevant in making the award.
The prime contractor shall be GDOT prequalified in work class 500 or 513 and provide at least three 3 successfully completed projects of similar scope and size within the past five 5 years. the prime contractor shall be gdot prequalified in work class 500 or 513 and provide at least three 3 successfully completed projects of similar scope and size within the past five 5 years.
Fixed liquidated damages are assessed for delays in completion, with charges starting at $50,000 for delays between 950 and 960 calendar days. these fixed liquidated damages are not established as a penalty but are calculated and agreed upon in advance by the county and the contractor due to the uncertainty and impossibility of making a determination as to the actual and consequential damages which are incurred by the county and the general public as a result of the failure on the part of the contractor to complete the work on time.
Failure to include the required documents, such as the contractor affidavit, will result in disqualification. failure to include this item will result in disqualification
****