City of Calexico invites bids for Cole Boulevard rehabilitation. Work includes cold milling, AC leveling course, ARAM membrane, ARHM overlay, ADA ramps, utility adjustments, and traffic control. Completion within 90 calendar days. Sealed bids due December 1, 2026, 2:00 PM. Non-mandatory prebid meeting November 12, 2026. Bid guarantee of 10% required. Award to lowest responsible bidder. Prevailing wages apply. Contractor must be licensed in California.
Project must be completed within 90 calendar days from date of contract award. To be completed within 90 calendar days from date of contract award.
Progress payments are made within 15 days after each estimate. A 10% retention is deducted from progress estimates. the city shall, within fifteen 15 days after the date of such estimates. . . pay to the contractor the amount stated in such estimates
The contract will be awarded to the lowest responsible bidder whose proposal complies with all requirements. the award of the contract, if it is awarded, will be to the lowest responsible bidder whose proposal complies with all the requirements prescribed.
Bids accepted only from contractors licensed in California. a bid will only be accepted from a contractor who is licensed in accordance with the provisions of chapter 9, division 3, of the business and professions code of the state of california
Liquidated damages apply for each day of delay in completing the work. the contractor shall pay for each and every day. . . that they shall be in default in completing the whole work. . . the sum named in the special provisions
Written protests must be filed within 10 days after receipt of an unsatisfactory decision. he shall, within ten 10 days after receipt of same, file a written protest with the public works directorcity engineer
Bids may be disqualified if required documents are missing, including proposal form, bid bond, and noncollusion affidavit. the bid may be considered incomplete and be disqualified if any of the following information is not provided.