Sealed bids for crack filling, seal coating, and striping at multiple park district locations. Bids due March 22, 2016 at 10:00 AM. Bid guarantee of 5% required. Performance and payment bonds required at 100% of contract price. Prevailing wage ordinance applies. Work must be substantially completed by July 29, 2016. Award to lowest responsible bidder. Site visit recommended but not mandatory.
Substantial completion is required by July 29, 2016, as stated: substantial completion date: july 29, 2016.
Monthly estimates may be presented by the first Monday of each month, with payments made within approximately 30 days after review, as stated: payments will be made within approximately thirty 30 days after review by the owner.
A minimum one-year warranty is required for all materials and workmanship, as stated: the contractor and/or manufacturer shall provide a minimum of one 1 year warranty for all materials and workmanship.
The contract will be awarded to the lowest responsible bidder, as stated: award of contract will be made to the lowest responsible bidder.
Bidders must examine all documents and visit the site to verify conditions, as stated: each bidder shall carefully examine all documents pertaining to the work and visit the site to verify conditions.
Failure to provide required bonds within five days may result in default, as stated: the failure of the successful bidder to supply the required bonds within five 5 days after the notice of award. . . shall constitute a default.
Bidders should visit the site to ascertain conditions, as stated: bidders should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work.
Failure to furnish a bid guarantee in the proper form and amount may cause rejection, as stated: failure to furnish a bid guarantee in the proper form and amount by the time set for opening of bids may be cause for rejection of the bid.