Repair services for Canby Utility facility damaged by an industrial explosion. Scope A includes non-permit-bound repairs to the administrative building, covered parking, and site, including roof replacement and interior repairs. Scope B includes permit-bound repairs to the maintenance warehouse, including structural, roofing, fire sprinkler, and electrical work. Mandatory prebid meeting and site visit on November 17, 2026. Bids due December 3, 2026, via Bid Locker. Prevailing wage project. Bid security of 10% required. Liquidated damages apply. First-tier subcontractor disclosure required.
Scope A substantial completion by February 24, 2027, and final completion by March 16, 2027. Scope B substantial completion by April 16, 2027, and final completion by May 4, 2027. contractor shall achieve: a scope a substantial completion on or before february 24, 2027 b scope a final completion on or before march 16, 2027 c scope b substantial completion on or before april 16, 2027 and d scope b final completion on or before may 4, 2027.
The contract will be awarded to the lowest responsive and responsible bidder. it will award the contract to the lowest responsive and responsible bidder.
Bidders must be licensed with the Oregon Construction Contractors Board (CCB) and provide a statement of qualifications. Bidders shall be licensed with the state of oregon construction contractors board ccb before bidding on public improvements contracts.
Liquidated damages of $1,000 per day for delays in substantial or final completion, plus additional $1,000 per day for operational interruptions. contractor will pay owner, or owner may withhold from sums due contractor, 1, **** for each day that expires after the applicable scope a or scope b substantial completion date until that scope is substantially complete.
Mandatory prebid meeting and site visit on November 17, 2026, at 9:00 AM. attendance at prebid meeting is required for a bid to be considered responsive.
Protests of specifications must be delivered at least 10 days before bid closing. a bidder may protest the specifications or contract terms and conditions by delivering a written protest on those matters to the owner not less than ten 10 days before bid closing.
Bids may be rejected for non-compliance, including failure to submit first-tier subcontractor disclosure by deadline, lack of CCB license, or failure to attend mandatory prebid meeting. failure to submit the completed firsttier subcontractor disclosure form by the statutory 4: 00 pm pt deadline shall result in immediate rejection of the bid as nonresponsive.