The project involves resurfacing the existing trail system, including asphalt overlay, milling, patching, and repainting. Bids are due March 12, 2026, at 2:00 PM. Questions must be submitted by March 9, 2026, at 5:00 PM. A performance bond and payment bond are required. The contract work must be completed within 75 consecutive calendar days of the commencement date recorded on the notice to proceed. Liquidated damages of $500 per day will be assessed for delays.
The contract work is to be finally and fully complete within 75 consecutive calendar days of the commencement date recorded on the notice to proceed. The contract work is to be finally and fully complete within 75 consecutive calendar days of the commencement date recorded on the notice to proceed.
Progress payments may submitted by the contractor based upon number of units completed as measured and agreed upon per article 32 measurement of quantities and as described in the project specifications. Progress payments may submitted by the contractor based upon number of units completed as measured and agreed upon per article 32 measurement of quantities and as described in the project specifications.
The contractor, in executing this contract, warrants that hesheit will be responsible for the maintenance or correction of any work completed under this contact that may become defective due to faulty workmanship or materials for a period of one year after final acceptance of the contract work performed. The contractor, in executing this contract, warrants that hesheit will be responsible for the maintenance or correction of any work completed under this contact that may become defective due to faulty workmanship or materials for a period of one year after final acceptance of the contract work performed.
The award of the contract, if it is awarded, will be to the lowest responsive, responsible bidder whose qualifications indicate the award will be in the best interest of the owner. The award of the contract, if it is awarded, will be to the lowest responsive, responsible bidder whose qualifications indicate the award will be in the best interest of the owner.
The contractors submitting a bid for this project must possess the proper license classification to perform the work elements contained in the specifications in accordance with north carolina general statutes and if selected, provide a copy of their active license to the owner. he contractors submitting a bid for this project must possess the proper license classification to perform the work elements contained in the specifications in accordance with north carolina general statutes and if selected, provide a copy of their active license to the owner.
Town reserves the right to assess liquidated damages of 500 per calendar day per property for failure to meet the above timelines. own reserves the right to assess liquidated damages of 500 per calendar day per property for failure to meet the above timelines.
Deadline for question submittal will be monday, march 9, 2026, at 5: 00 pm. Deadline for question submittal will be monday, march 9, 2026, at 5: 00 pm.