This is a Request for Quotation (RFQ) for the Baxter Family Housing Phase II Insulation Drago Wrap Vapor Barrier project. The Cook Inlet Housing Authority (CIHA) is seeking sealed quotes from responsible and responsive contractors. The scope of work includes furnishing and installing a vapor intrusion barrier system and all insulation work required for the project, adhering to local, state, and federal codes, including the Alaska Building Energy Efficiency Standard (BEES). Key tasks involve installing a minimum 20 mil polyethylene vapor barrier, thermal insulation, air sealing, duct insulation, and vapor retarders. CIHA will conduct a smoke test to confirm vapor barrier continuity. The anticipated start date is August 1, 2026, with phased building completion dates extending to September 30, 2027. Contractors must comply with administrative requirements, including submission of a safety plan, schedule of values, daily reports, submittals, certified payroll reports, Section 3 reports, and MBE/WBE reports. Federal Davis-Bacon wages are required. Quotes are due by April 30, 2026, at 2:00 PM Alaska Time. Questions are due by April 27, 2026, at 2:00 PM via email.
The bid notice states that quotes are due by April 30, 2026, at 2:00 PM Alaska Time. The anticipated start date for the work is approximately August 1, 2026, with phased building completion dates extending to September 30, 2027.
The bid notice refers to AIA Document **** sample for payment terms.
The bid notice mentions warranty of title and warranty of construction, with the latter running for one year from the date of final acceptance of the work, unless otherwise indicated.
The bid notice states that award will be made to the lowest priced, responsive and responsible offeror consistent with the terms of this RFQ.
The bid notice requires quotes from responsible and responsive contractors. It also mentions requirements for a current State of Alaska business license, contractors license, and Municipality of Anchorage contractors license.
The bid notice mentions that the penalty for making false statements in offers is prescribed by federal law at 18 **** also states that failure to submit required documents by the deadline may render the bid nonresponsive.
The last day for questions is April 27, 2026, 2:00 p. m. via email.