Sealed bids for CIPP relining of storm sewer pipes at various Jamestown locations. Bids due October 14, 2026, 10:00 AM. Bid bond 10% required. Work must start within 5 days of notice to proceed, substantial completion by December 18, 2026, final completion by December 31, 2026. Liquidated damages $100 per calendar day. Prevailing wage rates apply. Performance and payment bonds 100% each required. Contract may be extended one year.
Substantial completion is required by December 18, 2026, and final completion by December 31, 2026, as stated in the summary of work: substantial completion: december 18, 2026 and final completion: december 31, 2026.
Payments are based on unit prices for bid items, with progress payments for work performed. The contract states: payment will be made only for work performed in accordance with the drawings, specifications and contract documents.
The contract will be awarded to the lowest responsive and responsible bidder on the basis of the total bid as stated in the instructions to bidders.
Bidders must submit a statement of qualifications when requested, including construction experience and financial resources. The owner may reject bids if the bidder lacks adequate expertise, lack of prior experience with comparable projects, or lack of financial resources.
Liquidated damages of **** per calendar day apply for work not substantially completed by the deadline, as stated: the contractor shall make a payment to the city in the amount of one hundred dollars **** per calendar day until the violation is corrected.
Requests for interpretation must be received by the owner five or more business days prior to the date set for the receipt of proposals as stated in the instructions to bidders.
Bids may be rejected if they contain omissions, erasure, alterations or additions of any kind or if the bidder fails to provide required bid security, bonds, or insurance. The owner may also reject bids from non-responsible bidders.