Sealed bids due October 29, 2026, 12:00 noon. Mandatory pre-bid conference October 7, 2026, and mandatory site visit October 6, 2026. Bid bond or certified check for 5% of total base bid required. Award based on total bid price with local preference within 5%. Performance and payment bonds required at 100% of contract price. 10% retainage withheld. Liquidated damages $100 per day. Work must be completed within 135 calendar days after notice to proceed. One-year warranty on labor and workmanship. Questions due October 9, 2026, via email.
Work must be completed within 135 calendar days after notice to proceed. The notice states: shall complete all work requirements within 135 calendar days following the notice to proceed.
A 10% retainage is withheld from each payment until final payment. The document states: A 10 retainage will be withheld from each payment until final payment is made.
The contractor must guarantee labor and workmanship for at least one year. The document states: The contractor shall guarantee all labor and workmanship for minimum of one 1 year from date of completion.
The contract will be awarded based on total bid price, with a local preference. The document states: The contract, if awarded, will be based on total bid price and reserves the right to award bids to county businesses. . . within 5 percent of the lowest responsive and responsible bid.
Bidders must submit a qualification form, financial legal stability statement, and insurability statement. The document lists Bidders qualification form and Financial legal stability statement among required submittals.
Liquidated damages of $100 per day for delays. The document states: Liquidated damages in the amount of 100 damages shall be charged to the contractor for each day that the project is delayed beyond the completion date.
A mandatory site visit is scheduled. The document states: A mandatory site visit is scheduled for 2:00 pm, tuesday October 6, 2026, at rose hill cemetery main entrance **** riverside drive, macon, ga.
Questions and requests for interpretation must be submitted by October 9, 2026, at 3:00 pm. The document states: deadline for submitting questions is friday, october 9, 2026, at 3:00 pm.
Bids may be rejected if incomplete or irregular, or if required submittals are not furnished. The document states: the right of the owner to reject a bid if the bidder failed to furnish any required submittals on the date required. . . or if the bid is in any way incomplete or irregular.