Sealed bids due by 2:00 PM CDT on October 29, 2026, at Sumner City Hall. Public hearing on November 2, 2026. Work must commence between March 1 and April 15, 2027, with substantial completion by July 23, 2027, and full completion by August 27, 2027. Bid security of 10% required. Performance, payment, and maintenance bonds required. Davis-Bacon prevailing wages apply. Liquidated damages of $1,000/day for late substantial completion and $500/day for late full completion. Iowa resident bidder preference applies. Project funded by DWSRF and CDBG.
The project must be substantially complete by July 23, 2027, and fully complete by August 27, 2027. The contractor shall substantially complete the project by no later than july 23, 2027.
Payments are made based on estimates approved by the engineer, with 97% of work compensated and 3% retained. The contractor will be compensated for 97 of the work completed during a payment period, with the remaining 3 being retained.
A maintenance bond guarantees the improvement for four years after acceptance. shall also guarantee the maintenance of the improvement caused by failures in materials and construction for a period of four 4 years from and after acceptance of the contract.
Bidders must submit a fully completed bidder status form. failure to submit a fully completed and accurate bidder status form with the proposal may result in the proposal being deemed nonresponsive.
Liquidated damages of $1,000 per calendar day for late substantial completion and $500 per day for late full completion. liquidated damages of 1, **** per calendar day will be assessed for work not completed within the designated contract terms.
Bids received after the deadline will not be considered and returned unopened. bids received after the deadline for submission of bids as stated herein shall not be considered and shall be returned to the late bidder unopened.