Lamar University seeks a contractor for football stadium repairs at Provost Umphrey Stadium. Mandatory presubmittal conference on November 17, 2026. Proposals due December 9, 2026. Scope includes structural and concrete repairs, painting, joint repairs, column repairs, corroded steel connection replacement, handrail repairs, and removal of fixed seating. Evaluation based on qualifications (60%) and pricing (40%). Subcontracting plan required. Payment net 30 days. Prevailing wage applies.
Substantial completion is scheduled for August 1, 2027, as noted in the project schedule: august 1, 2027: substantial completion.
Payment is net 30 days: university will pay for work performed under this contract net 30 days in accordance with texas government code, section ****.
Best value selection: the university will evaluate and rank each proposal with respect to the best value selection criteria contained in this solicitation.
Respondents must submit a statement of qualifications, pricing and delivery proposal, and subcontracting plan: failure to return the required documents will result in the qualification being determined as nonresponsive.
Liquidated damages are stipulated: the amount of daily liquidated damages negotiated for the project shall be based upon a reasonable estimate of actual damages.
A mandatory presubmittal conference is required: a mandatory presubmittal conference will be held at the time and location described below on November 17, 2026.
Questions must be submitted by November 20, 2026: all questions regarding this solicitation shall be in writing to the point of contact listed in section 1. 8 no later than friday, november 20, 2026, at 2: 00 p. m. cstcdt.
Failure to submit required documents or attend the mandatory conference may lead to disqualification: failure to return the required documents will result in the qualification being determined as nonresponsive and the qualification will be rejected.