Construction contract for a 3-bed observation unit at Saint Louis VA Medical Center. SDVOSB set-aside. Proposals due August 25, 2026, 2:00 PM CT. Site visit on August 5, 2026 at 10:00 AM CST. Performance period 550 days. Bid guarantee required (20% of bid price, max $3,000,000). Payment and performance bonds required. Award based on Lowest Price Technically Acceptable (LPTA). Five evaluation factors: past performance, technical experience, key staffing, subcontractor experience, safety plan. Submit proposals electronically to ***@***. *. * due August 12, 2026.
Proposals are due by August 25, 2026, at 2:00 PM CT. The solicitation states: proposal due date: august 25, 2026, at 2pm ct to gislaine. dorvil@va. gov.
Payments will be made upon receipt and certification of the invoice. The document states: payments will be made upon receipt and certification of the invoice in accordance with the appropriate payment clause.
A warranty of construction for guarantee period services is required. The document states: warranty of construction for guarantee period services: x yes or no reference vaar ****.
The award will be based on Lowest Price Technically Acceptable (LPTA). The document states: the va will make the award based on the lowest evaluated price of proposals meeting or exceeding the acceptability standards for nonprice factors.
Offerors must be registered in SAM and VetBiz by the proposal due date. The document states: all contractors and joint ventures must be registered in sam and vetbiz by the proposal due date in order to be eligible for award.
A site visit is scheduled for August 5, 2026 at 10:00 AM CST. The document states: the site visit is scheduled wednesday, august 5, 2026 at 10: 00am cst. location: john cochran bldg. 16, rm. a208 on 2nd fl 10am cst.
All questions pertaining to the project are due by August 12, 2026, at 6:00 PM CST. The document states: all questions pertaining to this project are due by **** by 6pm cst.
Failure to provide required documentation may result in being deemed nonresponsive. The document states: those offerors not providing the documentation outlined in the proposal instructions to offeror will be deemed nonresponsive to the terms of the solicitation.
The estimated construction magnitude is between $500,000 and $1,000,000. The document states: estimate of construction magnitude for this project is 500, **** to 1, 000, ****.