City of Hastings seeks bids for design, build, install, test and commission a new generator excitation system for the gas turbine at Don Henry Power Center. Bids due by 4:00 PM on December 16, 2026. Bid bond of 5% required. Performance bond required within 10 days of award. Project completion by December 20, 2027. Liquidated damages of $1,000 per calendar day past completion. Payment within 30 days after acceptance. 5% retainage. 12-month warranty period. No faxed or emailed bids accepted.
Project completion date is December 20, 2027. Equipment delivery date is October 26, 2027. project completion date: december 20, 2027
Payment within 30 days after acceptance of material, equipment, and/or labor. to be paid by the purchaser, within thirty (30) days after the acceptance of material, equipment, and/or labor by the purchaser
12-month guarantee period beginning on date of final payment. the guarantee period shall begin on the date of final payment and shall end 12 months later
Bidders must be on approved bidders list or fill out plan holders submittal form. you are required to fill out the plan holders submittal form that is located on the city website
Liquidated damages of $1,000 per calendar day past project completion date. The liquidated damages for this project will be $1,**** per calendar day past the project completion date.
Written objection to engineer's decision must be filed within 30 days. either party may file with the engineer and the other party to the contract, within 30 days after receipt of the decision, a written objection to the decision
Bids received after deadline will be returned unopened. Any bids received after this time will be returned unopened to the vendor.