Renovation of restrooms at Saddle Rock Golf Course Clubhouse. Bid due November 18, 2026 at 3:00 PM MT via Bidnet. Optional pre-bid conference and site visit on October 30, 2026. Estimated cost $250,****,000. Substantial completion by February 26, 2027, final completion by March 26, 2027. Liquidated damages $500/day. Bid bond required (5%). 80% Colorado labor requirement. SBE program applies for contracts over $250,000. Project management via Projectmates PMIS.
Substantial completion by February 26, 2027, final completion by March 26, 2027. This project has a substantial completion date of february 26, 2027, with a final completion date of march 26, 2027.
Progress payments made about 30 days after application, with 95% of work completed and 5% retainage. The city shall make progress payments. . . on or about thirty 30 days after the submission by the contractor to the city of a proper application for payment.
Warranties commence on the date of substantial completion. Warranties required by the contract documents shall commence on the date of substantial completion unless otherwise provided in the notice of substantial completion.
Contract awarded to the lowest responsible bidder. It is the intent of the city to award a contract to the lowest responsible bidder provided the bid has been submitted in accordance with the requirements of the bidding documents.
Bidders may be required to submit a statement of qualifications including work performed in the last five years, available plant and equipment, and CPA-certified financial statements. The statement of qualifications shall include, at a minimum. . . work performed by the bidder in the last five years. . . plant, equipment and material. . . recent cpacertified financial statements.
Liquidated damages of $500 per calendar day for delay. contractor shall pay city five hundred and no100 dollars **** for each calendar day that expires after the times specified in paragraph 5. 02 a and b above until the completion dates are satisfied.
Optional pre-bid conference and site visit on October 30, 2026 at 11:00 AM MT. an optional prebid conference and site visit is scheduled for october 30, 2026 at 11: 00 am mt. attendance is optional, but highly recommended.
Written questions due November 4, 2026 at 3:00 PM MT. written questions deadline november 4, ****: 00 pm mt
Bids not submitted electronically via Bidnet by the deadline will be rejected. bids shall be submitted electronically. . . through the rockymountain epurchasing system bidnet and must be received no later than 2: 00 pm mountain time on november 18, 2026. bids received using another method such as mail, email, or handdelivery will not be accepted. late bids will not be accepted.
Estimated cost ranges from $250,000 to $300,000. The estimated cost for this project ranges from 250, **** to 300, ****.