Lump sum contract for drywall repair to level 4 finish, painting, and commercial wallcovering in city manager's suite and hall offices. Mandatory prebid meeting and walkthrough on 11/24/2026. Bids due 12/2/2026 at 9:00 AM. Two phases: Jan 4-13, 2027 and Jan ****, 2027. No substitutions for specified wallcovering and paint. 1-year warranty. 10% retainage. No bid or performance bond required. Payment within 30 days of invoice. Insurance requirements include CGL, auto, umbrella, and crime coverage.
Phase 1 city manager's suite: January 4 through January 13, 2027. Phase 2 hall offices: January 18 through January 27, 2027. Each phase shall be complete, including punch list, before the carpet installer mobilizes. each phase shall be complete, including punch list, before the carpet installer mobilizes in that area
Payment will be made within thirty (30) days of receipt of a correct and complete invoice, subject to acceptance of the work. payment will be made within thirty 30 days of receipt of a correct and complete invoice
Contractor shall warrant all workmanship and materials for one (1) year from the date of final acceptance. the contractor shall warrant all workmanship and materials for one 1 year from the date of final acceptance
The city will award to the lowest responsive, responsible bidder. the city will award to the lowest responsive, responsible bidder whose bid best serves the interests of the city
Bidders must attend mandatory prebid meeting, provide three references for similar commercial painting and wallcovering projects, and identify wallcovering installation firm with at least five years experience. the installing firm shall have specialized in commercial wallcovering for not less than five 5 years
If contractor fails to meet a phase window, city may complete work by other means and charge excess cost. the city may, after three 3 days written notice and failure to cure, complete the work by other means and charge the excess cost
A mandatory prebid meeting will be held and will include a walkthrough of both work areas. Bidders who do not attend will be deemed nonresponsive. a mandatory prebid meeting will be held at the date, time, and location shown in section i and will include a walkthrough of both work areas
All questions pertaining to this ITB shall be submitted in writing by email to ***@***. *. * in accordance with the timeline in section I. all questions pertaining to this itb shall be submitted in writing by email to ***@***. *. * in accordance with the timeline in section i
Failure to attend mandatory prebid meeting, submit all required documents, or complete all blank spaces on bid form may render bid nonresponsive. bidders who do not attend will be deemed nonresponsive and a blank, a dash, or no bid on any line may render the entire bid nonresponsive