Sealed bids for gas line relocation and installation along Grayson Highway. Bids due December 10, 2026, 2:00 PM local time. Prebid conference on November 16, 2026. Questions due November 27, **** bid bond required. 100% performance and payment bonds required. Work must be completed within 180 consecutive calendar days. Liquidated damages of $1,000 per day for documented delays. Bidder must have utility contractor's license and proof of three similar contracts of at least $400,000 each in the past five years.
The work shall be completed within 180 consecutive calendar days from the notice to proceed. the work shall be completed within 180 consecutive calendar days.
The city shall pay within 30 days of receipt of a payment request, with interest at 1. 2% per month if payment is delayed beyond 60 days. the city of lawrenceville shall pay to the contractor, within thirty 30 days of receipt of any payment request
Contractor warrants all work for one year after substantial completion and final acceptance. if within one year after the date of substantial completion and final acceptance of the work by the city. . . any of the work is found to be defective
Award will be made to the lowest responsive and responsible bidder. award will be made to the contractor submitting the lowest responsive and responsible bid.
Bidders must have a utility contractor's license, a permanent place of business, and proof of at least three similar contracts of $400,000 or more within the past five years. have done and to show proof of no less than three contracts of similar character to the work being bid, each with an original contract price of no less than 400, **** within the past five years.
Liquidated damages of $1,000 per day for documented delays. a reasonable amount to fully compensate owner for damage and loss it would incur. . . shall be at 1, **** per day if there is a documented delay
Bids may be withdrawn only in case of mathematical error, with written notice within two business days after bid opening. the bidder shall give notice in writing of his claim of right to withdraw his bid without penalty due to an error within two 2 business days after the conclusion of the bid opening procedure.
Failure to observe instructions, use city bidding forms, or acknowledge addenda may result in rejection. failure to use city bidding form and to acknowledge applicable addenda may result in a bid being deemed nonresponsive an automatic rejection.