Rehabilitation of one home in Adair County, including carpentry and roofing. Work must be completed in 20 working days, starting within two weeks of notification. Liquidated damages of $100 per working day for delays. Bids due October 23, 2026 at 5:00 PM. Mandatory bid response sheet and work write-up must be fully completed. TERO certification required for preference. Award to lowest, most responsive responsible bidder. Payment in one payment at 100% completion and acceptance. One-year warranty on workmanship. Site visit available by contacting David Keys. Davis-Bacon wage rates apply.
Work must be completed within 20 working days after notice to proceed. The bid states: this job must be completed in 20 working days.
Payment is made in one payment at 100% upon completion and acceptance. The document states: payments will be made in 1 payment at 100 statement of completion and acceptance of work approved by the hacn inspector.
Contractor must warranty work against faulty materials or workmanship for one year. The document states: shall warranty his work against faulty materials or workmanship for a period of one 1 year.
Award is based on the lowest and most responsive responsible bid. The document states: awarded to the responsible bidder whose bid is determined to be the lowest and most responsiveresponsible.
Bidders must complete the mandatory bid response sheet and work write-up. TERO certification is required for preference. The document states: to be considered a responsiveresponsible bidder, the mandatory bid response sheet and the work write up must be fully completed.
Liquidated damages of $100 per working day for delays beyond the contract end date. The document states: $ **** will be charged for liquidated damages to the contractor for each working day of extension over the contract end date.
Bidders can visit the job site. To schedule, contact David Keys at 918-506-9842. The document states: bidders can visit the job site and acquaint themselves with the exact nature of work to be performed.
Bids received after the deadline will not be considered. The document states: bids received after the deadline will not be considered.