RFP for comprehensive installation of athletic entry door replacement at Saline High School. Proposals due October 14, 2026 at 11:30 AM local time via BuildingConnected. Work includes interior and exterior door replacement, with interior doors completed before exterior. Contractor must obtain state building permit and include $10,000 allowance per building. Bid security of 5% required. Performance and payment bonds required for proposals $50,000 or more. Work scheduled December 19, 2026 to January 18, 2027, with completion during school break. References and insurance documentation required.
Final completion of work is January 18, 2027. The project schedule requires substantial completion by January 3, 2027. final completion of work january 18, 2027
The contractor warrants work will comply with applicable laws for a minimum of two years from completion. in accordance with all applicable federal, state, and local laws and regulations for a minimum of two 2 years from completion of the work
Contractors must provide references showing current work for public school districts, preferably similar sized projects. detailed evidence that the contractor is currently providing work for other public school districts preferred or similar sized projects
Bid security shall be forfeited as liquidated damages if the contractor withdraws its proposal after the due date or fails to execute the contract. the bid security shall be forfeited as liquidated damages, and not as a penalty
For a site visit, contact Mark Paulus at ***@***. *. * or **** a site visit, please contact mark paulus at ***@***. *. * or 248 ****
Requests for clarification must be received by 4 p. m. on October 7, 2026. school district will not respond to any request for clarification received after 4 p. m. on october 7, 2026
Proposals received after the due date will not be accepted. proposals or proposal revisions received after the due date will not be accepted or considered