The City of Stanton seeks proposals for facility assessment report services for the public safety center sheriff station upgrades project. A mandatory site meeting is scheduled for October 7th, 2026. Proposals must be submitted by October 20, 2026, at 10:00 a. m. The assessment must evaluate existing conditions, recommend prioritized improvements (Category A for grant-funded scope, Category B for other needs), and provide cost estimates. The project has an approximate construction budget of $749,000.
The final facility assessment report shall be completed within approximately 90 calendar days following the city's issuance of the notice to proceed. The consultant shall complete the final facility assessment report within approximately 90 calendar days following the city's issuance of the notice to proceed.
This work is to be performed for a not-to-exceed fixed fee, with progress payments based on tasks performed as identified in the payment schedule. The city will pay the consultant for work completed as identified in the payment schedule.
Proposals will be evaluated based on factors including staffing capabilities, technical competence, qualifications and experience, approach to work, past performance record, and efficiency and timeliness. submitted proposals will be evaluated based on the following factors, but may not be limited to just these factors: criteria approximate weight staffing capabilities technical competence.
The city is requesting proposals from California licensed architects and/or professional engineer consultants with a minimum of five years of experience. The city of stanton city is requesting proposals from california licensed architects and/or professional engineer consultants with a minimum of five 5 years of experience.
A mandatory site meeting will be held on Wednesday, October 7th at 10:00 a. m. A mandatory site meeting will be held on wednesday, october 7th at 10:00 a. m.
All questions and/or inquiries shall be submitted by Thursday, October 8th, 2026, at 5:00 p. m. all questions and/or inquiries shall be submitted by thursday, october 8th, 2026, at 5: 00 p. m.
Proposals will not be accepted from any consultant who did not attend the mandatory site meeting. Proposals will not be accepted from any consultant who did not attend the mandatory site meeting.
The approximate construction budget for Category A recommendations is $749,000. with consideration of the city's approximate construction budget of 749, 000.