Construction of sidewalk extension along **** Road. Mandatory prebid meeting on December 3, 2026. Bids due December 16, 2026 electronically. Bid bond 5%, performance and payment bonds 100%. Work plan required with bid. Award based on best value: price 40%, references 30%, qualifications 20%, work plan 10%. Liquidated damages apply. Retainage 5% until substantial completion. Completion by July 30, 2027 (substantial) and August 27, 2027 (final).
Substantial completion is July 30, 2027 and final completion is August 27, 2027, as stated: substantial completion: july 30, 2027 and final completion: august 27, 2027.
Payment is for work actually completed and accepted, with 5% retainage until substantial completion. The text states: the city will retain 5 of invoiced amounts until substantial completion.
The contract is awarded to the best-value contractor based on: price 40, reference considerationspast performance with the city 30, qualificationsexperience of team 20, and quality of work plan and approach 10.
Contractors must submit a work plan including project experience, organization, embankment compaction approach, subcontractors, and schedule. The text states: the contractor shall prepare and submit a work plan with the bid.
Liquidated damages are assessed for failure to reach completion dates, ranging from $500 to $5,800 per day based on contract amount. The text states: liquidated damages will be assessed as outlined in the sample contract.
Questions must be received by 12:00 noon on December 14, 2026. The text states: the deadline for receipt of questions from bidders in regards to this ifb is 12: 00 noon on december 14, 2026.
Bids may be considered nonresponsive if not submitted in the required manner, including missing signed addenda or bid bond. The text states: failure to submit a proposal in the manner indicated may be cause for it to be considered nonresponsive.