Furnish all labor, materials, equipment, and services to construct underground fiber infrastructure at intersections along and adjacent to I-225 and above-ground network improvements at two locations to connect city-operated traffic signals to the central traffic signal system. Mandatory prebid conference on October 6, 2026. Bids due October 21, 2026 at 2:00 PM via Bidnet. Bid bond of 5% required. Work must be completed within 70 working days. Liquidated damages apply per CDOT Standard Specifications **** program applies for contracts over $250,000. CDOT prequalification required.
The work must be completed within seventy (70) working days per the project special provisions. the contract documents require that all work, except landscape establishment, be completed within seventy (70) working days per the project special provisions.
Progress payments are made on the basis of applications for payment, with 95% of work completed paid and 5% retainage withheld. ninety-five (95) percent of work completed with the balance being retainage.
The contract is awarded to the lowest responsive, responsible bidder. award will be to the lowest, responsible, responsive bidder, based on the city's evaluation.
Bidders must have active prequalification status with the Colorado Department of Transportation. prior to submitting a bid for this project, the bidder shall have received prequalification status (active status) with the colorado department of transportation.
Liquidated damages apply for failure to complete work as prescribed, per CDOT Standard Specifications **** to complete the work as prescribed shall be considered as a breach of contract and subject to liquidated damages per colorado department of transportation (cdot) standard specifications ****.
Written questions must be submitted by October 12, 2026 at 3:00 PM. written questions deadline october 12, 2026 @3:00 pm.
Bids received using another method such as mail, email, or hand-delivery will not be accepted, and late bids will not be accepted. bids received using another method such as mail, email, or hand-delivery will not be accepted. late bids will not be accepted.
The estimated budget for this project ranges between $1,370,000 and $1,507,000. the estimated budget for this project ranges between 1,370,000 and 1,507,000.