Mandatory prebid conference on November 12, 2026 at 9:00 AM PT at Salem Army Aviation Support Facility 1, **** Turner Road, Salem, OR **** due November 24, 2026 by 10:00 AM. Project start 10 calendar days from NTP, substantial completion 90 days, final completion 120 days. CCB registration and public works bond required. Prevailing wage rates may apply if bid exceeds $50,000. No additional site access. Valid government issued photo ID required for facility access. Requests for clarification/protest due November 17, 2026 by 10:00 AM.
Substantial completion is required within 90 calendar days from issuance of notice to proceed, and final completion within 120 calendar days. The project start date is 10 calendar days from NTP. As stated: substantial completion: 90 calendar days from issuance of notice to proceed.
Contractor must be registered with the Oregon Construction Contractors Board and maintain a public works bond. As stated: at time of bid, contractor must be registered with the state of oregon construction contractors board, and maintain in full force and effect, the separate public works bond required by ors ****.
A mandatory prebid conference will be held on November 12, 2026 at 9:00 AM PT. Bids will only be evaluated from bidders who attend. As stated: bids will only be evaluated from bidders who are in compliance with this requirement.
Requests for brand approval, clarification, change, or protests must be received by November 17, 2026 by 10:00 AM. As stated: requests must be received by the poc by november 17, 2026 by 10: 00am.
Bids from bidders who do not attend the mandatory prebid conference will be rejected as nonresponsive. Also, bids must be received by the deadline. As stated: bids from bidders who do not comply with these attendance requirements will be rejected as nonresponsive.