Sealed bids are being accepted for the G. W. Oliver Road Bridge Construction Project. The project involves demolition, new bridge construction, and various roadway and drainage improvements. Bids are due by July 17, 2026, at 11:00 AM EDT. Substantial completion is required by August 31, 2027, and final acceptance by September 30, 2027. Liquidated damages of **** per calendar day apply for delays. Payment is due within 15 days of invoice receipt. A bid bond of 5% of the total bid is required. Contractors must be GDoT prequalified in work class 500 Concrete Structures. The county reserves the right to reject any or all bids.
Substantial completion is due by August 31st, 2027, and final acceptance by September 30th, 2027. he contractor shall achieve substantial completion deadline of the work and certification of same no later than august 31st, 2027 and shall achieve final acceptance deadline of the work and certification of same no later than september 30th, 2027.
Payment will be made within fifteen (15) days of receiving an approved invoice for quantities installed, with a retainage factor as specified in the bid package and contract. he contractor shall receive payment within fifteen 15 days ofreceipt of an approved invoice for quantities installed, with a retainage factor as specified in the bid package and contract.
The contractor shall reexecute any work that fails to conform to contract requirements and remedy defects due to faulty materials or workmanship appearing within one year from the date of completion and final acceptance, unless a manufacturer's warranty is longer. he contractor shall reexecute any work that fails to conform to the requirements of the contract and that appears during the progress of the work, and shall remedy any defects due to faulty materials or workmanship which appear within a period of one year from the date of completion of the contract and final acceptance of the work by the county unless the manufacturer of the equipment or materials has a warranty for a longer period of time, which warranties shall be assigned by contractor to county.
Award will be made to the lowest responsive and responsible bidder whose bid meets the requirements and criteria set forth. award will be made to the lowest responsive and responsible bidder whose bid meets the requirements and criteria set forth herein
Bidders must be GDoT prequalified contractors with a minimum prequalification in work class 500 Concrete Structures. from gdot prequalified contractors, with a minimum prequalification in work class 500 concretestructures
Liquidated damages of **** per calendar day will be assessed for failure to achieve substantial completion or final acceptance by the specified deadlines. he contractor shall continue the work and shall pay to the owner the sum of **** per calendar day as liquidated damages, and not as a penalty, for each calendar day that the work continues beyond the specified completion date
Claims for a change in contract time must be based on written notice within 30 days of the event occurrence. any claim for a change in contract time shall be based on written notice within 30 days of the occurrence of the event giving rise to the claim
Bids may be disqualified for late receipt, irregularities, unbalanced unit prices or extensions, unbalanced item values, incomplete proposal information, failure to comply with restrictions, or not appearing on the current GDoT prequalified contractor list. bids may be disqualified for: a receipt of the bid by the county past the stateddeadline b any irregularities c unbalanced unit price or extensions d unbalanced value of anyitems e failure to complete proposal information correctly or f failure to comply with restrictions toproposers, g bidder does not appear on the current gdot prequalified contractor list at the date andtime of the bid opening.