St. Tammany Parish Library- Mandeville Branch Reno
ST. TAMMANY PARISH LIBRARY MANDeville BRANCH RENOVATIONS Alternate 1: add work and materials for replacement of carpet a, indicated on drawings. Alternate 2: add work and materials for landscape installation plants, trees, new soils, as indicated on drawings.
AI helper
Monthly certificates for partial payment will be issued, with 90% of work performed and materials stored paid for contracts under $1,000,000, and 95% for contracts $1,000,000 or more. Final payment is due 45 days after filing acceptance and securing a clear lien certificate.
The contractor warrants all materials and equipment to be new and all work to be of good quality and free from faults or defects for a period of one year from the date of substantial completion. Specific warranties are also mentioned for asphalt shingles (25 years material, 10 years algae resistance) and window film (2 years).
The award of the contract, if it is awarded, will be to the lowest responsible bidder, in accordance with state law.
Bidders must be licensed by the state to do the type of work involved. The owner will conduct investigations to establish the responsibility, qualifications, and financial ability and stability of the bidder. Specific qualifications are also outlined for installers of storefronts, automatic entrances, and window film.
Liquidated damages will be assessed for failure to complete the work within the stipulated time, calculated per diem based on a table specified in the contract. The contractor agrees to pay reasonable attorney fees and costs in the event of breach of agreement.
The input does not explicitly state if a site visit is mandatory or optional, but it does mention that bidders shall visit the site and familiarize themselves with all conditions.
Samples are required for each type of product indicated, including carpet tile, sheet metal flashing, joint sealants, and textured finishes for plaster.
Protests must be filed in writing within ten calendar days after the basis of the protest is known, or should have been known, whichever is earlier. Protests based on alleged solicitation improprieties apparent before bid opening must be filed before those deadlines.