Solicitation for HVAC repairs (B522) and demolition (B414) at the 179th Cyberspace Wing, Mansfield, Ohio. Project magnitude is between $250,000 and $1,000,000. Bids are due by 1:00 PM local time on July 30, 2026. A mandatory pre-bid conference and site visit will be held on June 23, 2026. Registration is required for the conference and site visit. Bid guarantee (bid bond) is required. Award will be made to the responsible bidder whose bid is most advantageous considering price and price-related factors. The solicitation is 100% set-aside for small businesses. All questions must be submitted via email to ***@***. *. * by the fifth working day prior to bid opening.
The contractor shall begin performance within 30 calendar days and complete it within 180 calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable.
Payment will be made by the contracting officer. Invoices are to be submitted in 4 copies unless otherwise specified.
The document mentions warranty of construction as a clause, but specific warranty periods or terms are not detailed in the provided text.
Award will be made to the responsible bidder whose bid conforms to the invitation for bids and is most advantageous to the government, considering only price and price-related factors.
To establish responsibility, the apparent low bidder may be requested to submit information regarding their previous experience, business and technical organization, financial and bonding resources, and plant available for performing the work.
The document mentions that if the successful bidder fails to execute contractual documents or furnish bonds within 10 days after receipt of the forms, the contracting officer may terminate the contract for default. In case of default termination, the bidder is liable for costs exceeding their bid, and the bid guarantee is available to offset the difference.
A site visit will be held following the pre-bid conference on June 23, 2026. Registration is mandatory for all attendees due to security conditions.
Protests must be filed within the periods specified in FAR 33. 103. The NG protest decision goal is to resolve protests within 35 calendar days from filing.
Failure to furnish a bid guarantee in the proper form and amount by the bid opening time may be cause for rejection of the bid. Offers providing less than 90 calendar days for government acceptance after the date offers are due will not be considered and will be rejected.
The magnitude of the construction project is between $250,**** and $1,000,****.