01/20/2026 - USA | TN | CUMBERLAND COUNTY | CROSSVILLE | 38555 Small City
Water System Improvements - Catoosa Utility Dept. - Genesis Tank Rehabilitation
Water system improvements Contract **** Catoosa Utility Department Genesis Tank Rehabilitation Complete rehabilitation of 200, 000 gallon elevated water storage tank Sandblasting and recoating interior of tank Sandblasting and recoating exterior of tank Containment and installation of confined space placards Replacement of hardware, gaskets, safety climb system, and level indicator
AI helper
Bids must be submitted by February 18, 2026, at 11:00 a. m. Central Time. Prequalification information must be emailed by February 6, 2026, at 5:00 p. m. Central Time. The allotted time for construction is 120 calendar days. Liquidated damages for noncompletion are $1,000 per calendar day. The successful bidder must furnish performance and payment bonds. All bidders must be licensed general contractors. Questions concerning the bid documents must be received before 96 hours prior to the bid opening date and time.
The bid notice states he allotted time for construction of contract **** is 120 calendar days.
The prospective bidder shall provide evidence of general ability to perform similar work in a timely manner by submitting the project name, scope of work, allowed and actual time of completion, and a contact person for three previous projects of this general nature constructed within the past ten 10 years.
The bid notice states liquidated damages for noncompletion are 1, 000 per calendar day.
In compliance with tca **** and b the engineer will not issue addenda lessthan fortyeight 48 hours before the bid opening date and time further, any questionsconcerning the bid documents shall be received by the engineer before ninetysix96 hours prior to the bid opening date and time.