Interior plaster repairs at Soldiers and Sailors Memorial Building. Bids due online via Projectdog by Oct 22, 2026, 3:00 PM. General bidders must be DCAMM prequalified for historic building restoration. Subbids due Oct 15, 2026. Pre-bid conference Oct 7, 2026. Bid deposit 5% required. Performance and payment bonds 100% required. Work hours 7 AM-6 PM. Substantial completion by Feb 19, 2027; final completion by Mar 1, 2027. Liquidated damages $1,000/day.
Substantial completion by February 19, 2027, and final completion no later than March 1, 2027. achieve substantial completion by: february 19, 2027
The contract will be awarded to the lowest responsible and eligible bidder. notice of intent to enter into contract will be given to the lowest responsible and eligible bidder
General bidders must be prequalified by DCAMM for historic building restoration. general bidders shall be prequalified by the massachusetts division of capital asset management and maintenance dcamm for the category of historic building restoration
Liquidated damages of $1,000 per calendar day for failure to achieve final completion. liquidated damages will be in the amount of 1, **** per calendar day
A prebid conference is scheduled; access to the interior will not be provided at other times. access to the interior will not be provided at other times
General contractor questions must be submitted by October 19, 2026, 3:00 PM. general contractor questions must be submitted by october 19, 2026, 3: 00 p. m.
Failure to provide a valid DCAMM certificate of eligibility and update statement will result in bid rejection. failure to provide a valid dcamm certificate of eligibility and an update statement will result in the bid being rejected