Fulton County seeks design-build services for a new behavioral health crisis center in Alpharetta, GA. The project includes a 24-bed crisis stabilization unit and observation unit for 16 adults. Proposals due December 4, 2026, via BidNet Direct. Preproposal conference and site visit on October 20, 2026 (optional but encouraged). Bid bond required (5% of proposal price). Performance and payment bonds required (100% each). Substantial completion within 23 months, final completion within 24 months after notice to proceed. Liquidated damages $1,500 per day. Questions due October 30, 2026.
Substantial completion within 23 months and final completion within 24 months after notice to proceed. substantial completion, including issuance of a temporary certificate of occupancy, shall be achieved within twenty-three 23 months after issuance of the notice to proceed
Design-builder must conduct warranty review one month before end of warranty period. conduct a warranty review and facility inspection with county and facility staff one 1 month before the end of the general warranty period
Most advantageous to the county considering cost and evaluation factors. award will be made to the responsible proposer whose proposal is determined to be the most advantageous to the county, taking into consideration cost and the other evaluation factors
Proposers must be qualified firms with design-build capabilities. seeking qualified firms to provide design-build services and must include proof of E-Verify registration and contractor affidavit.
Liquidated damages of $1,500 per calendar day for incomplete work. for each calendar day that any work remains incomplete after the time allowed for completion, the designbuilder shall pay the county the sum of one thousand, five hundred dollars 1, 500
Site visit will be conducted immediately following the preproposal conference on October 20, 2026. a site visit will be conducted immediately following the preproposal conference on tuesday, october 20, 2026 Attendance is strongly encouraged but not mandatory.
Protests must be submitted within 3 business days after proposal due date for pre-due date grounds, or within 10 business days after knowing grounds. protests based on grounds that the protestor knew or should have known before the proposal due date shall be submitted within three 3 business days after the proposal due date
Proposals not meeting technical requirements will be deemed nonresponsive. proposals that fail to meet the technical requirements will be deemed nonresponsive Also, violations of no-contact provision may result in nonresponsive determination.