Onondaga County seeks bids for rehabilitation of Hillcrest Trunk Sewer using chemical injection grouting and CIPP lining. Work includes CCTV inspection, cleaning, grouting of joints and lateral connections, and lining of 8 and 10 inch clay tile sewers. Prebid meeting on 10/27/2026 at 2 PM strongly recommended. Bid security of 5% required. Performance bond of 100% required. MWBE participation required. Prevailing wage applies. Work must be completed by August 1, 2027. Bids due 12/11/2026 at 2 PM. Questions due 11/3/2026. Contract term from January 13, 2027 until project completion. Warranty: 2 years for grouting, 3 years for lining.
Work must be completed by August 1, 2027. The contract states: Work must be completed by august 1, 2027.
Payment is based on unit pricing with purchase orders. The document states: Compensation shall be paid based on unit pricing stated within the bid submission resulting in a contract award.
Grout sealing is guaranteed for 2 years and lining work for 3 years. The document states: the contractor shall guarantee the grout sealing of sewer pipe joints and lateral connections for two 2 full years and all lining work shall be fully guaranteed by the contractor for a period of three 3 years.
The contract will be awarded to the lowest responsive and responsible bidder. The document states: awarding the contract resulting from the bid, in whole or in part, to the lowest responsive and responsible bidder.
Contractors must have 5 years experience in similar work and CIPP contractors need at least 150,000 linear feet of CIPP history. The document states: Contractors shall have been in business for five 5 years performing similar work and the contractor shall have a history of at least 150, 000 linear feet of cippl work.
Failure to deliver may result in contract termination and disqualification from future contracts. The document states: Failure to deliver as specified may result in termination of the contract and may further disqualify your firm from receiving future contracts for at least two years.
A prebid meeting with site tour is strongly recommended. The document states: Bidders attendance at this meeting is strongly recommended to understand the scope of this project.
Samples may be required at the purchasing director's request. The document states: Samples are required to be furnished by the bidder at the request of the purchasing director.
Protests must be made within 3 days of bid opening. The document states: Protests of companies, products or services being offered from competing bidders must be made within 3 days of bid opening, in writing.
Bids lacking required bid security will not be eligible for award. The document states: Bids lacking bid security at the time of opening, when required, will not be eligible for award.