ACC seeks a general contractor for restroom renovations at Northridge Campus Buildings **** and 2000. Eight restrooms to be renovated including conversion of one office to accessible restroom. Estimated budget $990,000. Proposals due December 10, 2026. Optional solicitation conference and site visit on November 30, 2026. Work in occupied buildings with phasing requirements. Substantial completion by July 28, 2027. Liquidated damages apply. SLBE participation encouraged. Best value evaluation criteria include cost, past performance, project plan, personnel, safety, and business organization.
Substantial completion must be achieved by July 28, 2027, and final completion by August 25, 2027. The notice to proceed is anticipated for March 11, 2027. As stated: substantial completion must be achieved by july 28, 2027.
Progress payments are made with 5% retainage until substantial completion. The final 5% retainage is due upon full performance. As stated: acc will pay 95 of the amount due to the awarded contractor on account of progress payments, but will retain five percent 5 of the original amount.
The warranty against defects in contractor furnished material and workmanship is for one year from the date of final acceptance. A ten-month warranty walk is required. As stated: the respondents warranty against defects in contractor furnished material and workmanship shall be for one 1 year from the date of execution of the contract awardees final acceptance form.
Best value criteria include: total overall proposal cost 25%, past performance 25%, project plan 25%, personnel 10%, safety record 10%, and business organization 5%. As stated: total overall proposal cost 25 and quality, reliability, and successful experience of the respondents past performance. . . 25.
Respondents must be qualified general contractors, provide proof of insurability, workers compensation insurance, and evidence of licensure by appropriate state board if applicable. As stated: provide evidence of licensure by appropriate state board, if applicable.
Liquidated damages: $500 per calendar day for overall substantial completion delay, $750 per affected building per day for loss of restroom service, and $2,000 per affected building per day for building closure. As stated: overall substantial completion delay: 500 per calendar day.
An optional site visit will be held on November 30, 2026 at 10:00 a. m. CST, immediately following the solicitation conference. As stated: acc will host a site visit in regards to this project on monday, november 30, 2026 at the following time: o 10: 00 a. m. , cst.
Questions or comments must be submitted in writing by December 1, 2026 at 12:00 p. m. CST. As stated: deadline for questions: 12: 00 p. m. , cst december 1, 2026.
Proposals that do not include all required forms will result in automatic disqualification. Unsigned proposals are subject to rejection. As stated: proposals that do not include all required forms will result in automatic disqualification.
The estimated construction budget is $990,000. As stated: the estimated construction budget is 990, 000.