Sealed bids are solicited for the Kersey Clark Street Storm Sewer project, involving stormwater and roadway improvements. A mandatory pre-bid conference is scheduled for July 21st, 2026. Bids are due by August 11th, 2026, at 2:00 PM local time. The project includes pavement removal and replacement, new curb, gutter, sidewalk, waterline replacement, and storm sewer installation. Substantial completion is required by December 31st, 2026. Bidders must be qualified and licensed, and a bid bond of 5% is required. The contract will be awarded to the lowest responsible and responsive bidder, considering factors beyond price.
The work will be substantially completed by December 31, 2026, and complete and ready for final payment within 14 consecutive calendar days past substantial completion. The work, once started, will be substantially completed by december 31, 2026 and complete and ready for final payment within 14 days consecutive calendar days past substantial completion.
The town shall make periodic progress payments to contractor within 30 days following the project managers approval of the work completed. Progress payments shall be in an amount equal to 95% of the work completed. The town shall make periodic progress payments to contractor within 30 days following the project managers approval of the work completed.
Contractor shall warrant and guarantee all material furnished and work performed by contractor for a period of two years from the date of final acceptance of the work by the project manager. Contractor shall warrant and guarantee all material furnished and work performed by contractor for a period of two years from the date of final acceptance of the work by the project manager.
The contract will be awarded to the lowest responsible and responsive bidder complying with the terms and conditions, guidelines, and specifications presented in the bid request and these instructions to bidders. Also considered are: quality of product, past experience, qualifications, services offered, warranties, maintenance considerations, long-range costs, and delivery. The contract will be awarded to the lowest responsible and responsive bidder complying with the terms and conditions, guidelines, and specifications presented in the bid request and these instructions to bidders.
Bidders must be properly licensed under the laws governing their respective trades and be able to obtain insurance and bonds required for the work. A bidders qualification statement must be submitted with the bid. Bidders must be properly licensed under the laws governing their respective trades and be able to obtain insurance and bonds required for the work.
For each day final completion is delayed after the final completion date, contractor shall be assessed liquidated damages based on the contract price. For each day final completion is delayed after the final completion date stated in the construction contract, as modified through approved change orders, contractor shall be assessed the following amounts:
A mandatory pre-bid conference will be held at the Kersey Town Hall on July 21st, 2026, at 2:00 PM. Prospective prime bidders are required to attend. A mandatory prebid conference for all bidders will be held at the kersey town hall, 446 1st street, kersey on july 21st at 2:00 p. m. , local time.
Contractor shall furnish, upon the request of the project manager, samples, and shop drawings to the project manager, who shall review them for conformance with the contract documents. Contractor shall furnish, upon the request of the project manager, samples, and shop drawings to the project manager, who shall review them for conformance with the contract documents.
Questions and clarifications shall be submitted to the project engineer no later than ten days prior to the bid submittal. Questions and clarifications shall be submitted to the project engineer, scott larson, p. e. , ***@***. *. * no later than ten days prior to the bid submittal.
Any incomplete, false, or misleading information provided by any bidder shall be grounds for rejection of the bid. Firms not recording their presence at the pre-bid conference will not be allowed to submit bids. Any incomplete, false, or misleading information provided by any bidder shall be grounds for rejection of the bid.