The project involves HMA paving and miscellaneous related items on 99 road in Fairfield County. Bids are due on September 22, 2026, at 10:00 am. Substantial completion is required by May 31, 2027. Bidders must be legally qualified under South Carolina contractors licensing law and must submit a bid bond of 5% and furnish performance and payment bonds of 100% of the bid amount. The contractor agrees to a one-year warranty against defects.
Progress payments will be made on or about the 15th day of each month during performance of the work, with 95 percent of work completed as progress payment, less retainage. owner shall make progress payments on account of the contract price on the basis of contractors applications for payment on or about the 15th day of each month
The contractor agrees to a one-year warranty against defects, failures etc. caused by materials and workmanship, beginning on the date of final acceptance of punch list. the contractor agrees to a oneyear warranty against defects, failures etc. caused by materials and workmanship, beginning on the date of final acceptance of punch list.
The county in determining the lowest responsible bidder on each of the items shall consider, in addition to the bid prices, the quality, training, suitability and adaptability of the services required by this solicitation. the county in determining the lowest responsible bidder on each of the items shall consider, in addition to the bid prices, the quality, training, suitability and adaptability of the services required by this solicitation.
Bids will not be considered unless the bidder is legally qualified under the provisions of the south carolina contractors licensing law south carolina code of laws as amended. bids will not be considered unless the bidder is legally qualified under the provisions of the south carolina contractors licensing law south carolina code of laws as amended.
As liquidated damages for delay but not as a penalty, contractor shall pay owner as specified in the scdot 2025 standard specification, section 108. accordingly, instead of requiring any such proof, owner and contractor agree that as liquidated damages for delay but not as a penalty, contractor shall pay owner as specified in the scdot 2025 standard specification, section 108.
The bidder is expected to have become familiar with and take into consideration site conditions which may affect the work and to check all dimensions at the site. the bidder is expected to have become familiar with and take into consideration site conditions which may affect the work and to check all dimensions at the site.
All questions concerning the bid documents shall be in writing and submitted by cob september 14, 2026. all questions concerning the bid documents shall be in writing and submitted by cob september 14, 2026.
Failure to provide and maintain the required coverage will be grounds to declare the contractor in default of the contract. failure to provide and maintain the required coverage will be grounds to declare the contractor in default of the contract.