Bids are due by 2:00 PM on July 9, 2026, for demolition and clearing of the property at 117 S Osage, Shawnee, OK. The work includes removing structures, foundations, leveling the lot, waste disposal, utility capping, and grading. All demolition and debris removal must be completed by August 14, 2026. Payment is made upon completion and inspection of all work. The city reserves the right to reject bids. Contractors must provide proof of workers' compensation before obtaining a permit.
All demolition and removal of associated debris concerning property included with the bid packet will be completed by Friday, August 14, 2026. all demolition and removal of associated debris concerning property included with the bid packet will be completed by friday, august 14, 2026.
Payment will be made when all demolition, site clearance, debris removal, utility capping, final grading and cleanup of the entire site is completed and inspected. payment will be made when all demolition, site clearance, debris removal, utility capping, final grading and cleanup of the entire site is completed and inspected.
The best bid will be awarded on each individual site. he best bid will be awarded on each individual site.
Contractors must bring in proof of workers compensation before getting permit. contractor must bring in proof of workers compensation before getting permit.
Default in performance or failure to meet specifications authorizes the SURA to withhold payment and cancel the demolition of any remaining structures. default in performance or failure to meet specifications authorizes the sura to withhold payment and cancel the demolition of any remaining structures.
Default in performance or failure to meet specifications authorizes the SURA to withhold payment and cancel the demolition of any remaining structures. default in performance or failure to meet specifications authorizes the sura to withhold payment and cancel the demolition of any remaining structures.