Darbyshire Rd and Doc Darbyshire Rd Traffic Signal Installation
Traffic signal installation Steel strain poles, traffic signal equipment installation, storm piping 18 to 30, thermoplastic traffic striping, concrete sidewalk, maintenance of traffic, erosion and sedimentation control, and all appurtenances necessary for a complete job.
AI helper
The contractor shall complete the work no later than 180 days from the date of notice to proceed. to complete work within 180 consecutive calendar days of the date of noticeto proceed.
The owner shall make payment of the contract price and progress payments commenced with the amount of work done by the contractor less 10 of each payment. the owner shall make payment of the contract price and progress payments commenced with the amount of work done by the contractor less 10 of each payment.
The contractor shall guarantee all materials and workmanship for a period of one year from the date of final acceptance of the work by the engineer. The contractor shall guarantee all materials and workmanship for a period of one 1 year from the date of final acceptance of the work by the engineer.
The owner will consider factors other than price during the evaluation of bids and reserves the right to award the contract to the bidder whose bid is in the best interest of the project. owner will consider factors other than price during the evaluation of bids and reserves theright to award the contract to the bidder whose bid is in the best interest of the project.
The apparent lowest responsible bidder shall furnish the owner with information regarding their business, including a list of subcontractors exceeding 5% of the total base bid. The apparent lowest responsible bidder shall, upon written request and prior to the letting of a contract, furnish the owner with the following information relative to their business:
The contractor shall pay the owner the sum of **** per day for each and every calendar day of delay in achieving final completion of the work beyond said 180 days completion period. The contractor shall pay the owner the sumof **** per day for each and every calendar day of delay in achieving final completion of the work beyond said 180 days completion period.
A mandatory prebid conference will be held at the Colquitt County Public Works Office, 209 Destiny Drive, Moultrie, GA **** at 2:00 p. m. , September 8, 2026. a mandatory prebid conference will be held at the colquitt county public works office, 209 destiny drive, moultrie, ga **** at 2: 00 p. m. , september 8, 2026.
Requests for interpretations of drawings and specifications must be made in writing to the project engineer not later than five 5 days prior to receipt of proposals. requests for interpretations of drawings and specifications must be made in writing to the project engineer not later than five 5 days prior to receipt of proposals.
The owner reserves the right to reject the bid of any bidder whom it finds, after reasonable inquiry and evaluation, to be nonresponsible. owner further reservesthe right to reject the bid of any bidder whom it finds, after reasonable inquiry andevaluation, to be nonresponsible.
Bid Close Date: