Sealed bids for 2024 indoor courts complete refinishing due January 10, 2024 at 10:00 AM. Work includes sanding, sealing, painting lines, and finishing at multiple locations. Bid guarantee of 5% required. Performance and payment bonds required at 100% of contract price. Prevailing wages apply. Substantial completion by September 6, 2024. Award to lowest responsible bidder.
Substantial completion is required by September 6, 2024. The document states: substantial completion date: september 6, 2024.
Monthly estimates may be presented by the first Monday of each month, with payments made within approximately 30 days after review. The document states: payments will be made within approximately thirty 30 days after review by the owner.
A minimum one-year warranty is required for all materials and workmanship. The document states: the contractor andor manufacturer shall provide a minimum of one 1 year warranty for all materials and workmanship.
The contract will be awarded to the lowest responsible bidder. The document states: award of contract will be made to the lowest responsible bidder, as determined by the board of commissioners.
Bidders must examine all documents and visit the site to verify conditions. The document states: each bidder shall carefully examine all documents pertaining to the work and visit the site to verify conditions under which work will be performed.
Failure to provide required bonds within five days may result in contract termination and liability for excess costs. The document states: failure to comply with the conditions set forth in the contract documents shall result in the termination of the contract for default.
Bidders should visit the site to ascertain conditions affecting the work. The document states: bidders should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work.
Failure to furnish a bid guarantee in proper form and amount may cause rejection. The document states: failure to furnish a bid guarantee in the proper form and amount by the time set for opening of bids may be cause for rejection of the bid.