The project involves installing raised mid block crossings, new sidewalk, curb, gutter, landscaping, and replacing asphalt pavement on Coloma St. and Ebbtide St. Bids must be submitted by 11:00 am on Thursday, June 4, 2026. The contract will be awarded to the lowest responsive, responsible bidder. A valid California contractors license (A General Engineering) is required. A nonmandatory pre-bid conference is scheduled for May 13, 2026. The project must be completed within 60 calendar days.
The contract shall be awarded to the lowest responsive, responsible bidder as determined by the city from the base bid plus all alternates. city shall award the contract for the project to the lowest responsive, responsible bidder
This project requires a valid california contractors license for the following classification s: a general engineering. this project requires a valid california contractors license for the following classification s: a general engineering.
A nonmandatory pre bid conference is scheduled for may 13, 1: 00 p. m. to review the projects existing conditions at the intersection of coloma st and bridgeway. a nonmandatory pre bid conference is scheduled for may 13, 1: 00 p. m. to review the projects existing conditions at the intersection of coloma st and bridgeway.
The last day to submit questions prior to bid opening is 2pm tuesday may 26, 2026. the last day to submit questions prior to bid opening is 2pm tuesday may 26, 2026.
City may not accept a bid proposal from or enter into the contract with a bidder, without proof that the bidder is registered with the california department of industrial relations dir to perform public work pursuant to labor code **** may not accept a bid proposal from or enter into the contract with a bidder, without proof that the bidder is registered with the california department of industrial relations dir to perform public work pursuant to labor code ****.
The estimated construction cost is 810, 000 for the base bid, 83, 000 for additive alternative 1 and 34, 000 for additive alternative 2. the estimated construction cost is 810, 000 for the base bid, 83, 000 for additive alternative 1 and 34, 000 for additive alternative 2.