The bid is for the west esplanade avenue traffic signal upgrade project. Bids must be submitted electronically by april 16, 2026, and the public opening will be held at 2:30 p. m. on the same day. A nonmandatory prebid conference will be held on march 26, 2026. The project is exempt from state sales and use tax. The contractor must have a louisiana contractors license in the electrical work category. The work shall be substantially complete within 90 calendar days of the written notice to proceed and completed and shall be ready for final acceptance no more than 30 calendar days after substantial completion. The contractor shall provide a one 1 year warranty. The project is for the west esplanade avenue traffic signal upgrade project. Bids must be submitted electronically by april 16, 2026, and the public opening will be held at 2:30 p. m. on the same day. A nonmandatory prebid conference will be held on march 26, 2026. The project is exempt from state sales and use tax. The contractor must have a louisiana contractors license in the electrical work category. The work shall be substantially complete within 90 calendar days of the written notice to proceed and completed and shall be ready for final acceptance no more than 30 calendar days after substantial completion. The contractor shall provide a one 1 year warranty.
Payment to the contractor will be made in accordance with measurement and payment requirements for bid items and other requirements of the project specifications. Payment to the contractor will be made in accordance with measurement and payment requirements for bid items and other requirements of the project specifications.
Unless otherwise specified, all workmanship and materials must have at least a one 1 year warranty, in writing, from the date of deliveryacceptance of the project. Unless otherwise specified, all workmanship and materials must have at least a one 1 year warranty, in writing, from the date of deliveryacceptance of the project.
The award of the contract, if it be awarded, will be by the parish to the lowest responsive and responsible bidder whose proposal shall have complied with all the bid requirements. he award of the contract, if it be awarded, will be by the parish to the lowest responsive and responsible bidder whose proposal shall have complied with all the bid requirements.
Louisiana contractors license for this project must be in the following category: electrical work. louisiana contractors license for this project must be in the following category: electrical work.
Bidder agrees to pay, as liquidated damages, the sum of 500 for: 1 each consecutive calendar day after the agreed date of substantial completion that the work remains substantially incomplete, and 2 each consecutive calendar day after the 30th day following the actual date of substantial completion that the work has not been finally completed. bidder agrees to pay, as liquidated damages, the sum of 500 for: 1 each consecutive calendar day after the agreed date of substantial completion that the work remains substantially incomplete, and 2 each consecutive calendar day after the 30th day following the actual date of substantial completion that the work has not been finally completed.
All prospective bidders are invited to attend the nonmandatory prebid conference which will be held in the jefferson parish purchasing department at general government building 200 derbigny st. suite **** gretna, **** on march 26, 2026 at 10: 00 a. m. all prospective bidders are invited to attend the nonmandatory prebid conference which will be held in the jefferson parish purchasing department at general government building 200 derbigny st. suite **** gretna, **** on march 26, 2026 at 10: 00 a. m.
Written protest must be received within 48 hours of the release of the bid tabulation by the purchasing department. written protest must be received within 48 hours of the release of the bid tabulation by the purchasing department.
the range of the probable construction cost for base bid: range of the probable construction cost for alternate no. 1: range of the probable construction cost for alternate no. 2: range of the probable construction cost for alternate no. 3: range of the previous contract cap public work maintenance contract: the estimated cost range is for informational purposes only and may be subject to change. ange of the probable construction cost for base bid: range of the probable construction cost for alternate no. 1: range of the probable construction cost for alternate no. 2: range of the probable construction cost for alternate no. 3: range of the previous contract cap public work maintenance contract: the estimated cost range is for informational purposes only and may be subject to change.