USA | AK | ANCHORAGE COUNTY | ANCHORAGE | 99501 Midsize City
Municipality Of Anchorage - AK
Northwest Traffic Calming
northwood area traffic calming schedule a: road improvements schedule b: illumination improvements
AI helper
The project shall be substantially complete within forty-five (45) calendar days after the notice to proceed is issued, except for long lead items. All work, except for long lead items, shall be substantially complete by the start of preseason faculty operations. The contract completion date shall be within fifteen (15) calendar days after the substantial completion letter is issued. The total contract days for this project is sixty (60). Installation of items with long lead times delivered after the scheduled completion date shall be completed within fifteen (15) days of delivery to the contractor. The Municipality of Anchorage states, The contract completion date shall be within fifteen 15calendar days after the substantial completion letter is issued.
The bid notice states, Unless otherwise stated in the bidding documents, the contract, if awarded, shall be awarded to the responsible bidder who submits the lowest responsive bid.
The bid notice mentions a Responsible Bidder Questionnaire and requires a valid State of Alaska business license, State of Alaska contractor license, and Municipality of Anchorage contractor license. It also requires a SAM report or verification from sam. gov. The Municipality of Anchorage states, The following documents are required within five 5 working days of notification by the purchasing office. Failure, in whole or in part, to submit the documents required below may be grounds to determine the bidder as nonresponsible.
The bid notice states, The owner may withhold from any progress payment the sum of **** per day as liquidated damages for each and every calendar day that the substantial completion date is delayed beyond the contract completion date. The owner may withhold out of any progress payment the sum of 500 per day as liquidated damages for each and every calendar day that the final acceptance date is delayed beyond the contract completion date.
The bid notice states, Estimated construction cost: between: 500, 001 1, 000, 000.