March 12 - Giant Springs State Park Rock Wall and Sidewalk Repairs
combination truck and concrete mixer and transit mixer special provision: dry batch trucks distributor driver dumpman dump zone pay only applies to the truck driver classification. notrucks and similar equipment dumpster flat trucks zone pay was established for pilot car driver. lumber carriers lowboys pickup powder truck driverpower boom serviceman service truckfueltrucktireperson truck mechanic trucks with powerequipment warehouseman, partsman, cardex andwarehouse expeditor water trucks.
AI helper
This document outlines the general conditions for a construction contract in Montana, emphasizing safety, compliance with regulations, and the responsibilities of the owner, contractor, and subcontractors. It covers various aspects, including insurance, bonds, changes in work, time management, payments, and dispute resolution. The contract highlights the importance of safety, with the contractor responsible for site safety and compliance with safety laws. It also addresses hazardous materials, utilities, and the roles of the architectengineer. The document also includes provisions for equal opportunity and non-discrimination.
The work shall reach substantial completion within: fortyfive 45 consecutive calendar days.
The owner can approve the contractors payment request within hirtyfive 35 calendar days after it is received by the owner without being subject to the accrual of interest.
The contractor warrants and guarantees all materials and workmanship for the roofing system for a period of wo 2 calendar years from the date of final acceptance.
The contractor is required to be registered with the department of labor and industry under **** and **** mca prior to the contract being executed by the owner.
The contractor and his surety shall be liable for and shall pay to the owner the sums hereinafter stipulated as liquidated damages for each calendar day of delay until the work is substantially complete: one hundred and **** dollars ****.
By execution of the contract, the contractor acknowledges that it has reviewed and familiarized itself with all aspects of the contract documents and agrees to be bound by the terms and conditions contained therein. The contractor acknowledges that it has taken all reasonable actions necessary to ascertain the nature and location of the work.
Claims by either party must be initiated within 21 calendar days after occurrence of the event giving rise to such claim.