Project involves city park paving, including installation of asphalt speed control humps, adjustment of various utility structures, and resurfacing with asphalt wearing course. Bidders must submit proposals conforming to specifications, including bid bonds, qualification data, and affidavits. Work is to be completed within 45 calendar days of notice to proceed. Liquidated damages apply for delays. Contractor must provide insurance and comply with equal opportunity provisions. All questions must be submitted in writing to the City Engineer at least three days prior to bid opening.
The project must be fully completed within forty-five (45) calendar days after the contractor receives the notice to proceed. o fully complete the project within forty five 45 calendar days thereafter.
The city shall make a progress payment to the contractor on the basis of a duly certified and approved estimate of the work performed during the preceding period, retaining ten (10) percent. he city hall retain ten 10 percent of the amount of each estimate.
The contractor shall guarantee all materials and equipment furnished and work performed for a period of one year from the date of substantial completion. The contractor shall guarantee all materials and equipment furnished and work performed for a period of one year from the date of substantial completion.
Consideration will be given to various factors to determine the responsible bidder whose bid, conforming to the invitation for bids, is lowest, including but not limited to: bidder maintains a permanent place of business, suitability of bidders plant and equipment for work, bidders financial status, technical experience, past performance, contractor integrity, and compliance with public policy. Consideration will be given to various factors to determine the responsible bidder whose bid, conforming to the invitation for bids, is lowest, including but not limited to the following factors:
The bidder is required to provide bidder qualification data, including details of similar work performed, references, and information to enable the owner to judge their responsibility, experience, skill, business, and financial standing. The bidder is required to state in detail below, that work of a character similar to that included in the proposed contract he has done and to give reference and such other information as will enable the owner to judge of his responsibility, experience, skill, business, and financial standing.
Liquidated damages will be assessed for each calendar day the contractor is in default after the stipulated completion time. The daily charge is based on the original contract amount. for each and every calendar day that the contractor shall be in default after the time stipulated in the contract for completing the work.
Failure to execute the contract, file an acceptable bond, or provide other contract papers within ten (10) days of award can lead to annulment of the award and forfeiture of the proposal guaranty. if the contractor fails to execute the contract and file an acceptable bond and other contract papers within the ten 10 day period as stipulated, it shall be considered sufficient reason for the annulment of the award and forfeiture of the proposal Guaranty to the owner